Annexure IV
Technical Feasibility (To be submitted only in case of new connection)
1 Name of the Product(s),
Including bye-products &
its (their) use and its
manufacturing process in brief
1.2 Capacity : (No. of Units/Quantity in kg/
Volume in Litre per annum)
Capacity for
Each product Licensed Installed Operating
No. of working days in a month&
No.of shifts in a day
1.3 Locational advantages of existing
And/or proposed premises
With reference to availability of
Raw material, power,
Skilled labour, transport etc.
1.4 Whether clearance has been obtained
From the pollution control authority
1.5 PARTICULARS OF MACHINERY & OTHER FIXED ASSETS
As per Annexure II
1.6 RAW MATERIALS/COMPONENTS
(Please mention about the requirement & availability of imported and indigenous items separately)
2. UTILITIES
(Give comments on requirement, availability/adequacy, qualitative aspects, etc).
2.1 Power arrangements
Including standby
2.2 Water (Enclose certified xerox copy of sanction for water connection)
2.3 Fuel
2.4 Others (specify)
3. QUALITY CONTROL
3.1 Details of arrangement made for
Quality control like ISI/ISO/OHSAS etc.